The Pelican Hyrdoelectric Facility was constructed in the early 1940's and supplies electric power to the community. This project will replace the existing intake, wood flume and wood stave penstock with a new intake and HDPE penstock for continued reliable opertion.
The project is funded by the Denali Commision and administered by the Alaska Energy Authority.
Polarconsult is providing the engineering design of the upgrades to the intake, wing wall, penstock and surge tank as a consultant to Alaska Energy and Engineering who is designing upgrades to the switchgear in the Hydroelectric Power Plant and interconnection to a new diesel generation plant in the community.
The project is being constructed by the City of Pelican with project manaagement by CE2 Engineers.
This website is maintained by Polarconsult. All of the data on this web site is for informational purposes. While all efforts are made to insure the accuracy of the data on this site it is the responsibility of the end user of this data to insure the accuracy and suitability of the information and end user assumes all responsibility for actions and decisions based on this information.
For further assisantance contact the Alaska Energy Authority, Alaska Energy and Engineering, or Polarconsult.
Alaska Energy Authority
Alaska Energy and Engineering
Polarconsult Alaska, Inc.
polarconsult alaska, inc.
1503 West 33rd Ave., Suite 310
Anchorage, Alaska, 99503
tel 907.258.2420
fax 907.258.2419